-Implementation of needle pilings for the fire tank in the administrative capital Implementation of needle stakes with 73 stakes
Owner: Engineering Authority of the Armed Forces General
General Contractor: Target Engineering
Consultant: Moharram Bakhoum Office
-Implementation of excavation pilings with emptying, Gate 3, the capital Implementation of needle piles with a number of 91 piles, diameter 80 cm, length 17.5 meters
Owner: Engineering Authority of the Armed Forces
General Contractor: Arganza
Consultant: Moharram Bakhoum Office
-Implementation of drilling pilings by emptying Gate 4, the capital Implementation of needle pilings with a number of 250 pilings, diameter 80 cm, length 18.5 meters
Owner: Engineering Authority of the Armed Forces
General Contractor: Arganza
Consultant: Moharram Bakhoum Office